Breakthrough in the new energy industry GOTTOGPOWER micro-module data center has been successfully applied to the construction of China Huadian XX Informatization Dispatching Center project
[Abstract]: GOTTOGPOWER, as a data center energy solution supplier, relies on years of technological innovation strength, constantly excavates the needs of market segments, focuses on improving its own service capabilities and service levels, and provides better digital solutions for professional users.
GOTTOGPOWER, as a data center energy solution supplier, relies on years of technological innovation strength, constantly excavates the needs of market segments, focuses on improving its own service capabilities and service levels, and provides better digital solutions for professional users.
GOTTOGPOWER micro-module data center solution has been successfully applied to China Huadian XX Informatization project, providing a full range of critical infrastructure support for the security upgrade and efficient operation of Huadian XX Digitization center room, so that it can be updated and upgraded in security, service, operation and other aspects.
Project Overview
Project location: Huadian XX New Energy Informatization Dispatching Center , China.




Product Highlights
1、Precision air conditioning air flow organization diagram
As shown in the preceding figure, the two rows of cabinets face each other, and the aisle is sealed. Air conditioners are installed side by side with the cabinets. Air supply from the front and air return are used to ensure that the cooling air fills the aisle and ensures efficient cooling for each cabinet. The horizontal air supply between the closed cold aisle columns can eliminate the mixing of cold and hot air, improve the cooling efficiency of the air conditioner, and is more efficient and energy-saving than the air supply under the closed channel, reducing operation and maintenance costs, and does not require an elevated floor, and has lower requirements for the height of the floor. Because no elevated floor is required, the installation speed is fast, the bearing requirements on the floor are low, and the expansion is easy, the horizontal air supply mode between closed cold aisles is preferred.
2、Closed channel structure diagram


3、Power environment monitoring system architecture diagram

The monitoring system provides comprehensive monitoring of power systems (UPS, power distribution, battery packs, PDU), air conditioning systems (precision air conditioners, general air conditioners, fresh air units), environmental monitoring systems (temperature and humidity, smoke detectors, water leakage, switch quantities, etc.), and security systems (video, access control, infrared, door magnets). It adopts a B/S system architecture, eliminating the need for client installation and supporting simultaneous access by multiple clients. The system supports multiple alarm modes (sound and light alarms, email alarms, SMS alarms, and voice alarms over the phone), which can promptly remind administrators to carry out effective management and ensure the safety and reliability of modular data center.
Advantages of solution
Safe and Reliable
- The design scheme of GB50174-B + and Tier3 ensures the reliability of the system fundamentally;
- Using modular UPS power distribution, the mean time to failure of the distribution system can be greatly improved;
- The N+1 redundancy design is used to ensure the stable operation of the air conditioning cooling system;
- The module has the function of linkage and prevention, and the access control monitoring system can be set up to ensure the safety of the server equipment;
- The modular data center is equipped with a complete monitoring system, which can know the situation in the server room at any time and improve the reliability of the server room;
Green Energy Saving
- Using accurate air supply and cold and heat isolation technology, the cold air is fully exchanged with the server, avoiding the heat exchange of most of the cold air with the environment, so as to achieve the purpose of energy saving;
- The air conditioning is close to the heat source, which greatly shortens the air supply path and improves the utilization rate of cold air, thereby reducing energy consumption;
- The cold air and hot air are limited in a specific area, the return air temperature of the air conditioner is increased, the temperature difference between the air conditioner and the return air is enlarged, and the cooling efficiency of the air conditioner is provided, so as to achieve the purpose of energy saving;
- High frequency modular UPS, high output power factor, high system efficiency, more efficient energy saving;
- Compared with the traditional data center, the energy efficiency is effectively reduced by 30% ~ 50%, and the PUE value is controlled below 1.3;
- Taking 100KW load as an example, the micro-module data center saves about 600,000 yuan of electricity per year than the traditional , and the calculation is as follows:
100kw Load energy saving efficiency analysis